Lixin Shipyard completed the repair of "Royal Sky"

On September 17, Zhonghai Industrial Lixin Shipyard successfully completed the repair work of the "Royal Sky" round. The ship owner was very satisfied with the repair service and sent a thank you letter. The letter expressed satisfaction with the service attitude of the general manager, supervisor and business personnel of the plant, and appreciated the working attitude of the production staff.
The round entered Zhonghai Industrial Lixin Shipyard for repair on September 7. The repair works are mainly: mainframe 3#, 4# cylinder and 1#, 2# paying machine routine repair inspection; 1# fresh water pump overhaul; exhaust gas boiler and auxiliary boiler cleaning Overhaul, etc. This special project is a docking inspection.
During the factory, Lixin Shipyard communicated with the shipowner in time, and formulated detailed and detailed plans to overcome the large number of factories and ships, and the wide range of construction sites, to ensure the smooth development of all work. In the early stage of the ship's docking, it was found that there was a problem with the submarine valve of this round, which was very rare. The model was rare, and there was no stocking on the ship. It coincided with the holidays, and the factory was in a hurry. The factory replaced the subsea valve overnight. Thereby ensuring the docking period and winning the shipping schedule.
During the period, the turbine workshop was arranged according to the plan of the engineering department to ensure that the fitter can take care of the electrical and hull-related projects while ensuring the operation of the engine room, so as not to lose sight of one another. In order to make up for the lost time in the dock due to the failure of the tail shaft project, the fitter worked overnight for overnight operations. Under limited conditions, the various types of work were deployed as much as possible to ensure the smooth completion of the main and paying machines. Based on the concept of “owner first”, the staff of Lixin Factory has overcome the difficulties of ventilation and heat, and has overcome the difficulties of ventilation and heat in the ship's temporary side-to-side thrusting pipeline project. It has been working in a small closed compartment overnight and the project has been repaired.
The shipping schedule was 10 days, the ship schedule was tight, and the task was heavy. The staff of Lixin Shipyard overcame various difficulties and completed the repair work as planned, ensuring the progress and quality of the project, and making the “Royal Sky” round full of factory.