(I) Power Supply Section 1. When the conductivity meter is under low voltage AC power, both the indicator lamp and the filaments are off. Check if the power input, transformer primary, transformer secondary low voltage, etc. are normal.
2. The indicator light and each filament of the high voltage DC power supply can be bright, but the power eye tube does not emit green light, and when the replacement of the new one is ineffective, the high voltage DC power supply part can be checked first (a universal meter AC voltage 500V can be used. Two anode voltage). Check the transformer's secondary high voltage or wiring. If there is electricity and the cathode of the rectifier is measured with a DC voltage of 500V, there should be about +200V above ground. If there is no DC voltage or the voltage is low, replace the rectifier or filter capacitor. And pick up the contacts.
(2) Failure of the Oscillator and the Cathode Output Unit When the conductivity meter cannot measure the exact balance point with the high cycle, the oscillating tube and the cathode output tube may be replaced first. If the problem cannot be solved, the voltages of the two tubes must be measured. And wiring. The anode of the oscillating tube should be about 10V and the second gate should be +60V. The anode of the cathode output tube should be about +250V. Reusable high-impedance headphones or horns can also be used to track and check each signal point. This will find the problem.
(III) Problems with the Conductivity Meter Bridge The indicator blinks unstable when rotating the reading button or the override button during measurement or the balance point cannot be found at all.
1. First check the electrode system in the bridge circuit. Remove the electrode from the known resistance of about 1000 ohms. If the resistance is about 1000 ohms, then the problem is with the electrode or wiring. Replace or repair the electrode system. If it cannot be measured, continue to check.
2. In the reading button part, sometimes the sliding wire resistance inside the reading button is poorly contacted. Clean the contact point with a clean silk cloth or the like so that the contact can be good everywhere.
3. Many of the knobs are misaligned or poorly contacted due to internal band switches. They can be wiped and reset with a small amount of ethanol or trichloroethylene.
4. Capacitance Problems The conductivity meter sometimes blurs the edge of the indicator's light band and adjusts the bridge arm capacitance to a clear degree.
(4) Indicator failure 1. If the indicator beam edge is still blurred after the conductivity meter adjusts the bridge capacitance, the electro-ocular tube 6E1 or 6E2 can be replaced. The former's green fluorescent band moves in a fan shape, and the latter moves up and down. , And the wiring is different.
2. The indicator action is not sensitive. At this time, the amplifier tube and the electro-ocular tube can be replaced. If it is still not sensitive, check the voltage and wiring of each pole.
2. The indicator light and each filament of the high voltage DC power supply can be bright, but the power eye tube does not emit green light, and when the replacement of the new one is ineffective, the high voltage DC power supply part can be checked first (a universal meter AC voltage 500V can be used. Two anode voltage). Check the transformer's secondary high voltage or wiring. If there is electricity and the cathode of the rectifier is measured with a DC voltage of 500V, there should be about +200V above ground. If there is no DC voltage or the voltage is low, replace the rectifier or filter capacitor. And pick up the contacts.
(2) Failure of the Oscillator and the Cathode Output Unit When the conductivity meter cannot measure the exact balance point with the high cycle, the oscillating tube and the cathode output tube may be replaced first. If the problem cannot be solved, the voltages of the two tubes must be measured. And wiring. The anode of the oscillating tube should be about 10V and the second gate should be +60V. The anode of the cathode output tube should be about +250V. Reusable high-impedance headphones or horns can also be used to track and check each signal point. This will find the problem.
(III) Problems with the Conductivity Meter Bridge The indicator blinks unstable when rotating the reading button or the override button during measurement or the balance point cannot be found at all.
1. First check the electrode system in the bridge circuit. Remove the electrode from the known resistance of about 1000 ohms. If the resistance is about 1000 ohms, then the problem is with the electrode or wiring. Replace or repair the electrode system. If it cannot be measured, continue to check.
2. In the reading button part, sometimes the sliding wire resistance inside the reading button is poorly contacted. Clean the contact point with a clean silk cloth or the like so that the contact can be good everywhere.
3. Many of the knobs are misaligned or poorly contacted due to internal band switches. They can be wiped and reset with a small amount of ethanol or trichloroethylene.
4. Capacitance Problems The conductivity meter sometimes blurs the edge of the indicator's light band and adjusts the bridge arm capacitance to a clear degree.
(4) Indicator failure 1. If the indicator beam edge is still blurred after the conductivity meter adjusts the bridge capacitance, the electro-ocular tube 6E1 or 6E2 can be replaced. The former's green fluorescent band moves in a fan shape, and the latter moves up and down. , And the wiring is different.
2. The indicator action is not sensitive. At this time, the amplifier tube and the electro-ocular tube can be replaced. If it is still not sensitive, check the voltage and wiring of each pole.
As a professional PET preform mould manufacturer, we use the best material which avaiable in market. Our preform mould is suitable for all main brand of PET injection molding machine in market.
The principle of providing meticulous customize services to every customer by considering all aspects of requirements from product optimization and effectiveness in mold to manufacturing costs.
Your Preform Mould Expert!
Pet Mould,Preform Mould,Pet Preform Mould,Preform Injection Molding
WENZHOU WINIBER MACHINERY EQUIPMENT CO., LTD. , https://www.winibermachinery.com