Project Name: Qinglongsi Coal Mine Fire Fighting Comprehensive Building and 1#, 2# Apartment Building Project (August 2011 - March 2012, RMB 30 million)
Progress phase: Starting construction Area under construction: Shaanxi Construction period: August 2011 - March 2012 Major equipment: cranes, fire-fighting facilities, security facilities, water supply and drainage facilities, electrical facilities, ventilation facilities, lighting facilities. (for reference only)
Project Description:
The project is located in Qinglongsi, Xi’an, Shaanxi Province, and the construction of 1# and 2# dormitory buildings; the total construction area is 15720m2, 6 floors, and the height of the mouth is 23.5m; the brick-concrete structure, strong foundation, reinforced concrete strip foundation; the indoor-outdoor height difference 0.75 m (local 0.15m), 1# building/2# building ± 0.000 absolute absolute height of 1111.85m/1111.45m. Fire-fighting Ambulance Comprehensive Building Project; total building area of ​​2629.6m2, 2 floors (local 1st floor), cornice height of 7.5m; brick-concrete structure, reinforced concrete foundation, reinforced concrete strip foundation; where the fire garage is a single-layer reinforced concrete frame structure, Strong concrete, reinforced concrete independent foundation; indoor and outdoor height difference is 0.90m, ± 0.000 elevation 1110.20m. The total investment of the project is 30 million yuan.
Progress phase: Starting construction Area under construction: Shaanxi Construction period: August 2011 - March 2012 Major equipment: cranes, fire-fighting facilities, security facilities, water supply and drainage facilities, electrical facilities, ventilation facilities, lighting facilities. (for reference only)
Project Description:
The project is located in Qinglongsi, Xi’an, Shaanxi Province, and the construction of 1# and 2# dormitory buildings; the total construction area is 15720m2, 6 floors, and the height of the mouth is 23.5m; the brick-concrete structure, strong foundation, reinforced concrete strip foundation; the indoor-outdoor height difference 0.75 m (local 0.15m), 1# building/2# building ± 0.000 absolute absolute height of 1111.85m/1111.45m. Fire-fighting Ambulance Comprehensive Building Project; total building area of ​​2629.6m2, 2 floors (local 1st floor), cornice height of 7.5m; brick-concrete structure, reinforced concrete foundation, reinforced concrete strip foundation; where the fire garage is a single-layer reinforced concrete frame structure, Strong concrete, reinforced concrete independent foundation; indoor and outdoor height difference is 0.90m, ± 0.000 elevation 1110.20m. The total investment of the project is 30 million yuan.
Construction Unit: Yulin Shenhua Energy Co., Ltd. Postal address: Changxing Road, Yulin Economic and Technological Development Zone Post Code: 719000
Contact: Ma Yanbin, He Yuandian, 0912-8230878
Fax
Construction unit: Beijing Wujiao Construction Engineering Corps Postal address: No. 32A, Anwaimenwaiguan Street, Dongcheng District, Beijing Postcode: 100011
Contact: Yu Yufu Electric
Related news: Tower Crane Infrastructure information